UNIT 64 - PILOT PROJECT
There are no widely available references for this unit.
We have included a long handout if you want to give your
students some background.
UNIT 64 - PILOT PROJECT
Compiled with assistance from Warren Ferguson, Ferguson
Cartotech, San Antonio, TX
A. INTRODUCTION
- pilot project provides the first physical results from a
GIS project
- is usually the last major milestone prior to
corporate and technical commitment
- recognizes the difference between reading about the
system and actually experiencing how it operates
- a pilot is part of the effort to "sell" the system within
the organization
- the results of pilot projects can be shown to
decision-makers as evidence of the system's
immediate value
- provide a tangible way of communicating the
potential of the system to skeptics within the
organization
- some organizations may go to full production without a
pilot
- in this case may need to rework the first
deliverables as the system is "run in"
- this risks alienating users
- pilots are useful for
- verifying estimates of costs and benefits
- evaluating hardware, software, system and database
design, procedures and alternatives
- in summary, pilots provide a range of reduction of risks
associated with project before final commitment to full
production is made
Formats for pilot projects
1. demonstration of concepts
- a chance for the organization to see a similar
system running in production, evaluate its products
- will be a demonstration of limited facilities on a
small area, using a system which may not be part of
the final production system, mainly for development
and hands-on experience
- in some cases even the data may not be part of
the organization's operation
- provides early visibility of the system to
management and users
2. prototype
- a full-scale model of the future system
- designed to identify any problems not foreseen by
FRS and benchmarks, to finalize design and the
conversion process
- may be:
- a "Development and Technical Prototype" to test
code and learn the system
- an "Applications Prototype" demonstrating
potential applications development
- generally convert an entire region or operating
division of the organization from existing
procedures to the new system
B. MANAGEMENT OF A PILOT PROJECT
- the pilot project should be defined and managed as
effectively as the major project of which it is part
- objectives must be defined clearly
Objectives
- evaluate system design
- hardware and software
- system performance
- database design
- updating of cost estimates for development
- test alternatives
- ways of generating products
- formats for products
- evaluate map input and conversion procedures
- evaluate whether or not to use outside suppliers for
data input and conversion
- improve estimates of input and conversion schedules
and costs
- improve information on data sources
- test management procedures
- training for staff
- production scheduling
- system management
- maintenance schedules
- market system to end-users and management
Issues in pilot design
- enthusiasm and support of management
- if support is minimal, the pilot must be oriented to
building a sound business case for the system
- funds available
- an effective pilot will have a substantial cost
- to be successful the pilot must justify this cost
and the subsequent, larger cost of the production
system
- geographical area of pilot
- if the pilot covers a region within the
organization's service area, this region must be a
significant proportion of the total area
- level of staff experience
- pilot project design must consider the current level
of experience of the project staff
- must allow sufficient training and experience for
those involved to permit realistic evaluation of the
potential of the system
- the corporate environment
- success of the project depends on corporate climate
- how conservative, how risk-averse
Results of the pilot
- at bare minimum:
- experience in implementing a GIS project
- management approval to proceed with major project
- ideally, it will:
- reduces risk in all areas
- increases the effectiveness of the major project
- improves efficiency in the early stages of the major
project
- a pilot can result in:
- trained staff and users
- well-developed technical, managerial and production
procedures
- near-production computer code
- an improved implementation plan
- enthusiastic support of management and users
C. EXAMPLE PILOTS - AM/FM SYSTEMS
- all pilots are unique to their corporate and technical
context
- because of the major investments involved in AM/FM
projects, AM/FM installations provide good examples
of carefully planned pilot projects
Pilot projects in AM/FM
- first in late 1960s in Cheyenne, Wyoming, by Public
Service Company of Colorado
- showed that technology and software cost and
performance were not sufficiently advanced to
support a large AM/FM project
- some pilots today use consultants and hardware/software
environments that can produce results in 4 months
- these are generally for small municipalities and
utilities, less than 100,000 customers
- larger projects requiring investments in the $10 million
to $100 million range may require 1 to 2 year pilots to
meet design objectives
Salt River Project
Pilot comparisons
overhead - Comparison of several AM/FM pilots
- table summarizes 11 AM/FM pilots by size and
schedule
- length of time used and size are functions of:
- scope of pilot definition
- resource commitment
- corporate experience in AM/FM
- type of service area (urban/rural)
- system purchased
- contents of database
- range of applications demonstrated
- system requirements
REFERENCES
"Pacific Gas and Electric project history", see handout
following (7 pages).
EXAM AND DISCUSSION QUESTIONS
1. Review and discuss the handout provided on Pacific Gas
and Electric project history.
2. Summarize the arguments for and against the use of a
pilot project as part of the planning process for a major
GIS project.
Back to Geography 370 Home Page
Back to Geography 470 Home Page
Back
to GIS & Cartography Course Information Home Page
Please send comments regarding content to: Brian
Klinkenberg
Please send comments regarding web-site problems to: The
Techmaster
Last Updated: August 30, 1997.